logo

ERTEK BUILDING SYSTEM
RESEARCH AND TECHNOLOGY ON CONSTRUCTION

PRESENTATION AND PROPAGATION OF BUILDING TECHNOLOGY

 

home

What is the ERTEK system

  • The construction method in a glance
  • The ERTEK building system in a glance

Description of the attributes of the structural skeleton

  • Technical features
  • Elements of the structural skeleton
  • Reduced weight and anti-earthquake behavior

Economy of construction

  • Production of the structural skeleton
  • The utility of the structural skeleton as infrastructure for the completion of the construction
  • Consequences of the reduced time of production on the economy of the construction

Example case study of the ERTEK system

  • Production cost
  • Duration of the production process

Downloads

  • Time and cost schedule of a building project
  • 3D model of the structural skeleton
  • Visualization of the structural elements

 

Example case study of the ERTEK system

 

    We are going to describe the cost and time schedule of an imaginary case study of the ERTEK system application on a small three-floor building whose typical floor includes eight 3.60/3.60m slab units. The schedule includes the materials, the labor for the production of the structural skeleton, the stair construction and the pipework installation. The cost scheduling is based on the following price table:

Structural Steel 600€ per tn
Concrete 60€ per m3
Daily hire of an unskilled worker 75€ (social security included)
Daily hire of a skilled worker 105€ (social security included)
Daily hire (€) of a 10tn crane 200€
Daily hire (€) of a 40tn crane 300€

The results reported below were aquired by a spreadsheet (free to download) that allows general project scheduling, depending on both the project's specifications and the resources available.

 

 

Production cost

 

 

FLOORS

3

Plot covered area (m2)

Built-up area (m2)

SLAB UNITS IN ONE FLOOR

8

103,68

311,04

 

Quantity

Unit Value (€)

Total Value (€)

COLUMNS

72

29,36

2113,70

SLAB UNITS

24

401,67

9640,05

FOUNDATION UNITS

8

370,25

2962,02

STAIR UNITS
4
171,36
685,44

 

 

 

 

LABOR

 

 

7995,00

 

 

 

 

Total Project Price (€)

 

 

23396,22

Price per m2 (€)

 

 

75,22

The comparative cost of resources for the aforementioned case study is given by the following table:

 

RESOURCES

Volume (m3)

Weight (kg)

Price (€)

Price %

MATERIALS

Structural Steel

0,661

5187,154

3112,29

13,30

Bolts - Nuts - Washers

0,006

48,245

57,89

0,25

Structural Steel of joints

0,341

2674,778

3209,73

13,72

Wire mesh

0,519

4073,627

2444,18

10,45

Concrete

85,139

204332,781

5108,32

21,83

Expanded Polysterine

24,480

0,00

1468,80

6,28

Material Totals

111,145

216316,585

15401,22

65,83

LABOR

Blinding concrete with wire mesh

 

 

300,00

1,28

Column production

 

 

1500,00

6,41

Pre-slab production

 

 

2130,00

9,10

Foundation

 

 

285,00

1,22

Assembling

 

 

1890,00

8,08

Pipework

 

 

870,00

3,72

Stairs

 

 

420,00

1,80

Concrete casting

 

 

600,00

2,56

Labor Totals

 

 

7995,00

34,17

 

 

Duration of the production process

Labor Prerequisites (days) Duration (days)
Blinding concrete with wire mesh   2
Column production 2 3
Pre-slab production 5 3
Foundation 8 1
Assembling 9 3
Pipework 10 2
Stair Units 10 2
Concrete casting 12 4
Total project duration (days)   16

 

pinax

    The duration of each work is reported in the yellow fields, while the overall duration of the works that constitute preconditions is reported in the purple fields.